Please be advised that this schedule may change due to weather and existing conditions found while performing the tasks below. This work may impact traffic and require lane and sidewalk closures limiting access to driveways and entrances to businesses.
What to Expect for the Week of December 5, 2022, to December 9, 2022
Detours
- Eastbound detour from Pleasant Street to Maple Street to Hayden Rowe will be used Monday-Friday
- Eastbound detour from Grove Street to Maple Street to Hayden Rowe will be used on an as needed basis.
Project Wide
- Electric manhole work East Side of Project
- Continue underground service connections between the Muffin House and Church Street
West Side of Project
- Continue winterizing project (finish paving any unfinished driveways and continue placing brick/granite walkways)
- Area of focus will be between Wood Street and the Fire Station
Working hours for the project are from 7am to 3pm. No detours, one lane closures or road closures are allowed between 7am and 9am.
For the most up to date information about the Main Street Corridor project please visit the Town’s project website at https://hopkintonmainstreet.com.
The Town of Hopkinton appreciates your patience and consideration while
we work to support MassDOT’s project to revitalize our downtown infrastructure.