MassDOT released the following schedule for the week of November 7, 2022 to November 10, 2022.
Please be advised that this schedule may change due to weather and existing conditions found while performing the tasks below. This work may impact traffic and require lane and sidewalk closures limiting access to driveways and entrances to businesses.
What to Expect for the Week of November 7, 2022, to November 10, 2022 (no work on November 11 – Veterans Day)
Detours
• The eastbound detour from Grove Street to Maple Street to Hayden Rowe will be used Monday-Thursday
• The eastbound detour from Pleasant Street to Maple Street to Hayden Rowe will be used Monday-Thursday
135/85 Intersection
• Cement concrete driveways at Country Farm Liquors (3 Cedar St), Post Office, Shell Gas Station, and CVS
• Concrete sidewalk work at the 135/85 intersection
East Side of Project
• Continue installing conduit services between the Muffin House and Hayden Rowe
• Eversource vault work between the 135/85 intersection and Ash Street
West Side of Project
• Install beveled curbing for sidewalk on the south side between the Fire Station and Pleasant Street
• Gravel and grading for sidewalks on the south side between the Fire Station and Pleasant Street
• Eversource vault work between the 185/35 intersection and Claflin Ave.
Working hours for the project are from 7am to 3pm. No detours, one lane closures
or road closures are allowed between 7am and 9am.
For the most up to date information about the Main Street Corridor project please
visit theTown’s project website at https://hopkintonmainstreet.com
The Town of Hopkinton appreciates your patience and consideration while
we work to support MassDOT’s project to revitalize our downtown infrastructure.